Mine Construction

  • December

    VPC signed a contract with THYSSEN SCHACHTBAU for drilling of freezing boreholes of vertical mine shafts.

  • October

    First cubic meter of concrete was poured at the base of a shaft mouth at the Talitsky area of VPMSD.

  • May

    Construction of a temporary road from Zheleznodorozhny settlement to the Talitsky mine site was completed.