Mine Construction
-
December
VPC completed construction and finishing works at the mine rescue brigade building.
-
November
VPC completed construction of water intakes for the concrete mixing station.
-
October
VPC completed construction of a road to the explosives warehouse.
-
September
VPC completed earthworks at the explosives warehouse.
-
August
VPC completed general construction of the ventilation building with a heater for the cage shaft.
-
July
Installation of water supply and discharge system at the site was completed.
Water wells were renovated for the period of shaft sinking.
-
June
Installation of metalwork and walling for the headframe, and of the skip shaft infrastructure facilities was completed.
General construction of main fan unit with air heater for the skip shaft was completed.
-
May
Installation of metalwork and walling for the headframe, and of the cage shaft infrastructure facilities was completed.