Mine Construction

  • December

    VPC started preparation of freezing plants for operation.

  • November

    VPC completed general construction of the frame crane platform.

  • October

    VPC completed construction of a warehouse for packaged products.

  • May

    VPC completed installation of fire tanks at the temporary explosives warehouse construction site.

  • March

    A site-wide compressed air system was installed.

  • February

    VPC finished construction of the acetylene and oxygen cylinder storage facilities.

  • January

    A fence was erected around the temporary explosives warehouse and the facilities for treatment of rainwater and sewage during the shaft sinking period.

    VPC completed construction of the parking lot for a fuel truck owned by contracting company US-30.