Mine Construction
-
March
Start of rock freezing operations at Cage Shaft No. 2
-
April
Start of Cage Shaft No. 2 sinking
-
June
Start of rock freezing operations at Skip Shaft No.1
Commissioning of a weighing house
-
July
Start of Skip Shaft No.1 sinking
-
September
Concrete mixing station was commissioned to enable shaft construction using special concrete