Field Development Project

  • December

    Engineering design for sylvinite mining at the Talitsky area of Verkhnekamsk potassium-magnesium salts deposit was submitted for review and approval to the Federal Reserves Committee (Rosnedra).
    Working documents were obtained for construction of vertical mine shafts

  • August

    Contracts were signed to design external power supply and railroad facilities at the Talitsky mine.

  • May

    A contract was signed with Novgorod GIAP for general design and design documentation for the Construction of a mining and processing facility at the VPMSD Talitsky area. Stage 3: Construction of surface complex.

  • April

    VPC signed a contract for designing the external natural gas supply of the Talitsky mine.